One week of delay = £1 million in lost profit | Construction delays explained
4 Nov 2025 · 1 min

1:08
A short YouTube explainer by William Doyle MRICS about the financial impact of construction delays. The speaker gives a worked example: on a £40–50m project typical prelims can be about £25,000 per week; with profit margins around 2–2.5% a one-week critical delay equates roughly to £1m of lost profit. The video stresses the importance of contemporaneous records to evidence delay assessments.
Questions this video answers
£25,000 per week
Around below 2%; example uses 2–2.5%
Roughly £1,000,000 in lost profit (equivalent to having to win and deliver £1m of extra work)