One week of delay = £1 million in lost profit | Construction delays explained

4 Nov 2025 · 1 min
1:08

A short YouTube explainer by William Doyle MRICS about the financial impact of construction delays. The speaker gives a worked example: on a £40–50m project typical prelims can be about £25,000 per week; with profit margins around 2–2.5% a one-week critical delay equates roughly to £1m of lost profit. The video stresses the importance of contemporaneous records to evidence delay assessments.

Questions this video answers

£25,000 per week

Around below 2%; example uses 2–2.5%

Roughly £1,000,000 in lost profit (equivalent to having to win and deliver £1m of extra work)

Chapters

More from William

1:02:20
youtube.com

Episode 11 NEC4 Webinar Series - Communicating Correctly

1mo ago
1:02:21
youtube.com

NEC4 Clause 13 Explained: Communicating Correctly | Gather Webinar

1mo ago
1:00:18
youtube.com

NEC4 Communication Done Properly

1mo ago
0:57
youtube.com

Project Documents in Gather | Organise Files with Folders

1mo ago
1:01
youtube.com

Construction Weather Data, Linked to Every Shift Record | Gather

2mo ago
1:29
youtube.com

AI for quantity surveyors

3mo ago
0:32
youtube.com

Costain stopped treating subcontractors like outsiders

3mo ago
0:46
youtube.com

The tool Costain's QS team refused to give up

3mo ago
0:21
youtube.com

Why your site team and QS team keep missing each other

3mo ago
0:20
youtube.com

The commercial edge nobody talks about

3mo ago
1:06
youtube.com

Search first. Ask questions later.

3mo ago
See all content