Why Are You Asked to Accelerate in Construction? Reasons revealed!

In this video, the speaker recounts a construction scenario where a subcontractor was instructed to accelerate work to meet a deadline. After completing the accelerated work, the subcontractor submitted a variation claim for the extra effort, but the client refused payment, arguing that the acceleration was requested because the subcontractor was already late. The speaker highlights the critical lesson that whenever a party is asked to accelerate, they must first clarify the underlying reason—whether the contractor is late and the client is compensating for extra resources, or whether the client’s own delay is causing the need for acceleration. Understanding who bears responsibility for the additional costs is essential to avoid denied claims and financial loss.